Jacksonville Harbor Deepening Project complete through

[ May 27, 2022   //   ]

Federal, state, and local leaders joined JAXPORT and the US Army Corps of Engineers (USACE) Jacksonville District on May 23 to celebrate the completion of the Jacksonville Harbor Deepening Project through JAXPORT’s Blount Island Marine Terminal. The project deepened 11 miles of the federal shipping channel—from the sea buoy to Blount Island—to a depth of 47 feet from its previous depth of 40 feet.
The 47-foot harbor provides the channel depth needed for larger ships to call Blount Island to and from destinations worldwide and allows existing ships calling Jacksonville to carry more cargo on board. In addition, the project includes a new turning basin allowing larger vessels to turn around at Blount Island berths.
“Florida’s seaports are economic drivers for our state and serve as gateways to domestic and international markets,” said Florida Department of Transportation (FDOT) Secretary Jared W. Perdue, P.E. “Through FDOT’s strategic investments, our seaports continue to expand and modernize to meet the needs of Florida’s growing economy and communities. The JAXPORT Harbor Deepening Project communicates to the world that Florida is open for business and demonstrates Florida’s unwavering commitment to strengthen and grow supply chains while providing a safe, resilient, competitive, and dynamic multimodal transportation system.”
“When JAXPORT began this deepening journey nearly two decades ago, the goal was to build the port of the future,” said JAXPORT Board Chair Wendy Hamilton. “With today’s completion of deepening through Blount Island—the future is here, and JAXPORT is equipped to meet the needs of the nation’s supply chain for generations to come.”
In coordination with deepening, JAXPORT completed more than $100 million in berth enhancements this month to enable the SSA Jacksonville Container Terminal (JCT) at Blount Island to simultaneously accommodate two post-Panamax container ships. In early 2023, terminal operator SSA Atlantic will welcome three new eco-friendly 100-gauge container cranes, bringing the JCT’s total to six.
“Anchored by harbor deepening, well over half a billion dollars in infrastructure improvements have been recently completed or are currently underway to improve our container capabilities at Blount Island,” said JAXPORT CEO Eric Green. “With the support of our federal, state, and local partners, JAXPORT is open for business and ready to serve the needs of our customers while creating local jobs here in our community.”
Deepening through Blount Island was completed three years ahead of the original project schedule. The total funding to date is $420 million funded through a public-private partnership between the federal government, State of Florida, City of Jacksonville, JAXPORT, and SSA Atlantic.
The Jacksonville Harbor Deepening Project creates or protects 15,000 jobs throughout the supply chain, including trucking, warehousing, and distribution. The initial feasibility study for the project began in 2005, and construction started in February 2018.
In addition to the deepening, berth improvements, and new cranes, more than $70 million in terminal enhancements—funded by SSA and a grant from the US Maritime Administration (MARAD)— are also underway to expand container capacity at the SSA JCT. By spring of 2023, SSA will complete the first three of seven construction phases, producing approximately 31 acres of newly paved and improved operating area. The total project of approximately 93 acres will be complete by the end of 2024, allowing the SSA JCT to accommodate 500,000 TEUs (containers) annually.
“SSA would like to thank JAXPORT, the Army Corps of Engineers, and all our state and local officials for their commitment to this historic event,” said SSA Vice President of Florida Operations Frank McBride. “Forty-seven feet of water positions Jacksonville among the deepest ports on the East Coast, further enhancing the capabilities of the SSA JCT as an international cargo gateway.”
The Jacksonville Harbor Deepening Project is a 13-mile federally authorized project. The current funding model covered the completion of the first 11 miles. The final two miles are authorized and under review.